DOT&PF completed the Juneau Creek Bridge design as a steel girder bridge. Construction of the bridge abutments is anticipated to begin in 2024, with construction of the bridge continuing through 2027.
Juneau Creek Bridge will be:
Work for the 2025 construction season has ended. Completed work includes:
Work has resumed for the 2026 season, with main focus on girder launch preparation. The launch is anticipated to take place following Memorial weekend. Crews will be working Monday through Saturday. Both Bean Creek and Resurrection Trails remain open for use.
Other work planned for the 2026 season includes pouring abutment backwalls, wingwalls, and shear keys.
Last Updated: April 22, 2026
Bridge Looking Southeast - April 2026