• Project Overview
  • Construction/Gallery
    • Stage 1A
    • Stage 1B
    • Stage 2
    • Stage 3 & 4
    • Stage 5
    • Stage 6
    • MP 61.5
    • Connections
  • Project Contacts
  • More
    • Project Overview
    • Construction/Gallery
      • Stage 1A
      • Stage 1B
      • Stage 2
      • Stage 3 & 4
      • Stage 5
      • Stage 6
      • MP 61.5
      • Connections
    • Project Contacts
  • Project Overview
  • Construction/Gallery
    • Stage 1A
    • Stage 1B
    • Stage 2
    • Stage 3 & 4
    • Stage 5
    • Stage 6
    • MP 61.5
    • Connections
  • Project Contacts

Sterling Highway MP 45-60 Project

Sterling Highway MP 45-60 ProjectSterling Highway MP 45-60 ProjectSterling Highway MP 45-60 Project

Stage 2 (Design 2020–2023, Construction 2024–2027)

DOT&PF completed the Juneau Creek Bridge design as a steel girder bridge. Construction of the bridge abutments is anticipated to begin in 2024, with construction of the bridge continuing through 2027.

 

Juneau Creek Bridge will be: 

  • Highest crossing in the state at 285 feet (Hurricane Gulch is approximately 250 feet)
  • longest single-span bridge in the state since 1982
  • longest erected and launched bridge in the state

Current Work

As of May 5, 2025, work completed consists of the drilling for all of the drilled shafts (abutments and pier locations).  All below-ground work for the drilled shafts has been completed (steel casings, reinforcing steel and concrete).  


Girders are expected to arrive in June 2025. Reinforcing steel installation in the East abutment and forming and pouring the temporary back-span structures will support the girders as they are assembled and launched. 


Work on the East pier caps will commence in May 2025, with focus moving to the West side following. By the end of the 2025 construction season, all pier caps and abutments will be poured and ready for launch in 2026.  

Last Updated: May 5, 2025

Stage 2 Videos

Straddle Crane Assembly 1

Straddle Crane Assembly 2

Straddle Crane Assembly 3

Bridge Launch Assembly

Bridge Piling Driving

Stage 2 - June 2024

Stage 2 Photos

East Bridge Abutment-May 2025


    Copyright © 2025 Sterling Highway MP 45-60 Project - All Rights Reserved.


    Powered by

    This website uses cookies.

    We use cookies to analyze website traffic and optimize your website experience. By accepting our use of cookies, your data will be aggregated with all other user data.

    Accept