Stages 3 and 4 consists of the middle section (off the existing alignment) of the project to the east and west of the Juneau Creek Bridge. These stages will establish staging and disposal sites, road embankment, drainage, wildlife crossings and the Slaughter Gulch pedestrian crossing.
Riprap placement at Sterling Hwy MP 57 will begin on Monday, October 14th and work is anticipated to last until October 25th. Expect up to 10-min delay for work activities. Flaggers operations will be in effect from 7am to 7pm, Monday thru Friday.
Crews continue to work on the installation of Wildlife Crossing #2. This is a 21-foot diameter undercrossing being installed on the east side of the project corridor.
Crews installing culverts and ditch lining through the east side corridor.
Blasting operations to last until mid-October at the Slaughter Ridge creek/trail crossing.
Last Updated: October 4, 2024
Wildlife Crossing #2b