Stages 3 and 4 consist of the middle section (off the existing alignment) of the project to the east and west of the Juneau Creek Bridge. These stages will establish staging and disposal sites, road embankment, drainage, wildlife crossings, and the Slaughter Gulch pedestrian crossing.
Completed and In Progress:
Progress to Come:
Impact to Travel and Recreation:
Last Updated: May 5, 2025
Slaughter Gulch Structure Excavation-May 2025